The newly upgraded Wembley Park Station can handle a 70 per cent increase in passenger numbers, up from 22,000 people per hour to 37,500. Construction began in April 2004 and was substantially completed in March 2006.

Improvements include:

  • Extended commuter ticket hall
  • Widened stairs to Olympic Way, used during events
  • New events ticket hall
  • Five new passenger lifts
  • Extended canopy on platforms 4 and 5
  • Upgraded platforms
  • Upgraded waiting rooms
  • New escape stairs
  • Better security and information systems

Wembley Park Station
New stairs from Olympic Way to event day ticket hall

Wembley Park
Refurbished ticket hall

 

The improvements to the station were unveiled in March 2006 by Mayor of London, Ken Livingstone and ex-England footballer, David Seaman. For full details on this event click here